软题库 培训课程
当前位置:信管网 >> 在线考试中心 >> 试题查看
试题题型【单选题】
试题内容

With a clear SOW a contractor completes work as specified,but the buyer not pleased with the result.The contract is considered to be()。
A、incomplete because the buyer is not pleased
B、incomplete because the specs are incorrect
C、complete because the contractor is satisfied
D、complete because the contractor meets the terms and conditions of the contract


相关试题