(  )is the  application  of planned, systematic  quality activities toensure that the project will employ all processes needed to meet requirements.
A. Quality assurance (QA)
B. Quality planning
C. Quality control (QC)
D. Quality costs


相关试题

70题:

项目经理在进行项目质量规划时应设计出符合项目要求的质量管理流程和标准,由此而产生的质量成本属于( )。
A. 纠错成本
B. 预防成本
C. 评估成本
D. 缺陷成本

答案解析与讨论:www.cnitpm.com/st/1238427.html

71题:

Project(  )is an uncertain event or condition that, if it occurs, hasa positive or a negative effect on at least one project objective, such as time,cost, scope, or  quality.
A.risk
B.problem
C.result
D.data

答案解析与讨论:www.cnitpm.com/st/1239427.html

72题:

Categories of risk response are (  ).
A.Identification, quantification, response development, and response control
B.Marketing, technical, financial, and human
C.Avoidance, retention, control, and deflection
D.Avoidance, mitigation, acceptance, and Transferring

答案解析与讨论:www.cnitpm.com/st/1240427.html

74题:

(  ) is primarily concerned with  defining and controlling what is and is not  included in  the  project.
A. Project  Time  Management
B. Project  Cost  Management
C. Project  Scope  management
D. Project  Communications Management

答案解析与讨论:www.cnitpm.com/st/1242428.html

75题:

A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(  ).
A.assign  change  tasks to project  members
B.call  a meeting of the  configuration  control  board
C.change  the  scope  baseline
D.postpone the modification until a separate enhancement project is funded after  this project  is completed according to the  original  baseline