1、 The project schedule is more than a document that lays out the activities over time to representthe time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used bythe roject management team to( ).
A.Measure, delay, record, distribute , analyze, and direct
B.Plan, schedule, monitor, control, report, and forecast
C.Promote, highlight, monitor, control, forecast, and report
D.Emphasize, visualize, analyze, conceptualize, report and record
信管网参考答案:B
项目进度表是项目管理的一种时间维度,比时间安排更为重要。因此,项目管理团队使用该进度计划来()。
A、 测量、延迟、记录、分发、分析和指导
B、 计划、计划、监控、控制、报告和预测
C、 推广、突出、监控、控制、预测和报告
D、 强调、形象化、分析、概念化、报告和记录
查看解析:http://www.cnitpm.com/st/1018.html
2、 Which of he following Project Scope Management peocesses involves subdividing the major project deliverables into smaller, more manageablecomponents( ).
A.Scope Planing
B.Scope Verification
C.Scope Change Control
D.Scope Definition
信管网参考答案:D
以下哪个项目范围管理流程涉及将主要项目交付物细分为更小、更易管理的组件()。
A、 范围规划
B、 范围验证
C、 范围变更控制
D、 范围定义
温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!
信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。
信管网软考课程由信管网依托10年专业软考教研倾力打造,官方教材参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。
发表评论 查看完整评论 | |