软题库 培训课程
当前位置:信管网 >> 分类练习 >> 文章内容
未指定试题:duringprojectclosureaprojectsponsorcompl
来源:信管网 2020年06月04日 【所有评论 分享到微信
试题分类:未指定

During project closure a project sponsor complains that the project did not increase the department’s knowledge of Java programming and therefore, the project is not complete. The customer has accepted the project. The project manager determines that all stated objective and deliverables have been met. He does not find evidence that Java programming was an objective .A review of project correspondence shows no mention of the deliverable. The project manager should:
A、close project
B、re-plan the project to include the new objective
C、meet with the team to discuss the issue and find a resolution
D、get the project stakeholders involved to help resolve the issue

试题出处:http://www.ruantiku.com/shiti/3505613088.html
在下面提交答题后即可查看答案与考友试题分析
我的答案与分析  查看全部答题与分析  

扫码关注公众号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,官方教材参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

推荐文章