第1题: The( )Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project’s requirements.
A.Planning
B.Executing
C.Monitoring and Controlling
D.Closing
Quality planning tools are often used to help plan effective quality management activities.( ) is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
A、Benchmarking
B、Quality metric
C、Quality checklist
D、Brainstorming
某集成企业在进行风险定性分析时,考虑了风险的几种因素:①威胁,指风险对项目造成的危害程度;②机会,指对项目带来的收益程度;③紧迫性,对风险亟待处置的程度;④风险发生的概率。关于该公司的定性风险分析,下列说法中,( )是不正确的。
A.①×③×④的值越大,则表明风险高,应考虑优先处理
B.②×③×④的值越大,则表明机会大,应考虑优先处理
C.①×②×④的值越大,则表明风险高、机会大,应考虑优先处理。
D.②×④的值越大,则表明机会大,应考虑优先处理
在信息系统安全技术体系中,环境安全只要指中心机房的安全保护。以下不属于该体系环境安全内容的是( )。
A.设备防盗器
B.接地和防雷击
C.机房控制
D.防电磁泄漏
省市信息产业主管部门负责对( )信息系统集成资质进行审批和管理。
A.一、二级
B.三、四级
C.本行政区域内的一、二级
D.本行政区域内的三、四级
在项目实施中间的某次周例会上,项目经理小王用下表向大家通报了目前的进度。根据这个表格,目前项目的进度( )。
A. 提前于计划7%
B. 落后于计划18%
C. 落后于计划7%
D. 落后于计划7.5%
项目论证是确定项目是否实施的依据,(1)不属于项目建设方项目论证的原则。(2)不属于项目建设方项目论证的内容。
(1)A、合规
B、实施便利
C、科学预测
D、重视数据资料
(2)A、招标文件的编制
B、项目组织设置的合理性
C、资金筹措的依据
D、项目的工艺技术
在OSI参考模型中,数据链路层处理的数据单位是()。
A.比特
B.帧
C.分组
D.报文
针对应用程序或工具在使用过程中可能出现计算,传输数据的泄露和失窃,通过其他安全工具或策略来消除隐患属于安全保护措施中的()
A.应用安全
B.物理安全
C.介质安全
D.数据安全
软件开发过程中的技术评审的目的是()
A、评价软件产品,以确定其对使用意图的适合性,表明产品是否满足要求
B、监控项目进展的状态,评价管理方法的有效性
C、从第三方的角度给出开发过程对于规则、标准、指南的遵从程度
D、评价软件开发使用的技术是否适用于该项目
温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!
信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。
信管网软考课程由信管网依托10年专业软考教研倾力打造,官方教材参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。
发表评论 查看完整评论 | |